Loop 281 Widening and Railroad Overpass
Location Longview, Texas
Owner Texas Department of Transportation
Client Texas Department of Transportation
- Alternatives Development and Analysis
- Construction Phasing Plan Development
- Controlled-Access Highway (Non-Interstate) Design
- Corridor Study
- Cost Estimate Development
- Culvert Design
- Design Study Report Development
- Final Plans, Specifications, and Estimates (PS&E)
- Highway/Roadway Design
- Intersection Analysis/Design
- NEPA Documentation
- Pavement Evaluation/Design
- Public Outreach/Involvement
- Railroad Crossing Design (Grade-Separated)
- Right of Way Evaluation
- Shop Drawing Review
- Signal Design
- Stormwater/Pavement Drainage Design
- Utility Coordination
- Value Engineering Evaluation
To accommodate increased traffic volumes, the Texas Department of Transportation reconstructed and widened a 1.5-mile section of Loop 281 around southwest Longview and constructed a new railroad overpass for Loop 281 at the busy intersection with the Union-Pacific Railroad and FM 2087. Lochner was the prime consultant for this project from the initial route study through to final design.
During the route study, Lochner developed a series of alternatives, which were presented in a value engineering forum to design professionals and engineers. Particular issues included the close proximity of the FM 2087 intersection and the Loop 281/SH 31 interchange to the existing at-grade railroad crossing, which posed a challenge in designing and constructing a new overpass while maintaining access to intersecting streets and nearby industrial facilities. The selected alternative relocated a section of FM 2087 to integrate the FM 2087 traffic with the SH 31 interchange.
During the final design stage, Lochner developed plans, specifications, and estimates for the 1.5-mile mainline widening from four to six lanes; the relocation of 1,500 feet of FM 2087; and the construction of a 500-foot-long, 104-foot wide, prestressed concrete I-girder span bridge over the UPRR. Lochner also designed intersection modifications at LP 281 and the SH 31 entrance/exit ramps.
Related Projects
Port of Long Beach On-Call Professional Transportation Planning Services
Supporting the premier U.S. gateway for trans-Pacific trade. Our planning team has a long history supporting the Port of Long […]
Alliance Water Phase 1B Seg-B Pipeline
In 2018, Alliance Water, a Regional Water Authority serving Buda, Kyle, San Marcos, and the Canyon Regional Water Authority, enlisted […]
SR 907 (Alton Road) Reconstruction, 43rd Street to East of Allison Road
State Route 907 (Alton Road) is a four‐lane divided highway that runs north–south along Miami Beach’s Biscayne Bay coastline. The […]